New Ramp from I-66 East to Route 28 North Opening on or about July 8

About the Project

Cedar Lane

On May 15, 2020, the Cedar Lane bridge over I-66 closed for about six months for reconstruction to accommodate the widening of I-66. Find information about construction, detours, and bus routes below. Watch a video overview hereSubmit questions, comments, and other feedback to the project team here.

The Cedar Lane bridge over I-66 is being rebuilt to accommodate the widening of I-66 and will include a shared-use path and wider sidewalk, as well as a nearby connection to the new shared-use path being built along I-66.

Get a closer look at what’s planned through the Transform 66 Interactive Map.

Planned Six-Month Closure of Cedar Lane Bridge

The Cedar Lane bridge closed on May 15, 2020, for demolition and reconstruction that will last until late November 2020. Closing the bridge for this period will reduce the duration and impacts of construction on travelers and surrounding neighborhoods to about six months, compared to a partial closure that would have taken more than two years to complete.

Benefits of this approach include:

  • Neighbors will experience fewer nights of noise from bridge demolition activities
  • Drivers on I-66 will have fewer months of extended lane shifts for bridge pier construction
  • The project team will maximize construction activity over Metrorail tracks during the planned Orange Line shutdown from Memorial Day to Labor Day

Ask questions or provide comments about construction plans by calling 703-662-3892, emailing transform66@vdot.virginia.gov, or submitting through the comment form.

The piers for the existing Cedar Lane bridge (shown in orange) must be demolished to make room for the wider I-66. The new bridge (shown in gray) is wider than the old bridge and will require just one pier.

Construction Update (Updated June 15, 2020)

Recent Construction Progress:

  • The northside bridge abutment has been demolished.

  • Demolition of the bridge deck was completed on June 10. 

  • Bridge beams over I-66 West were removed the night of June 8. Bridge beam removal over I-66 East finished June 13.

  • The bridge piers along I-66 West and I-66 East have been demolished.
  • View the construction flyer for more information about project construction.

Upcoming Construction Activities:

  • Demolition of the southside bridge abutment will finish this week, with work occurring during daytime hours.  
  • The remaining bridge pier (adjacent to Metrorail) will occur during overnight hours, but has not yet been scheduled.
  • Excavation has begun for the new northside bridge abutment.
  • Work schedules are subject to change based on weather and construction progress.

Upcoming Traffic Impacts:

  • I-66 East and West will be reduced to a single travel lane during overnight hours June 23-25 between Nutley Street and Gallows Road for utility relocation at Cedar Lane. Drivers should expect periodic 20-minute stoppages between midnight and 4 a.m. nightly.
  • Work schedules are subject to change based on weather and construction progress. 

Only the center pier remains of the old Cedar Lane Bridge. Excavation for the new north bridge abutment has begun. (June 14)

What Neighbors Can Expect

Some construction and demolition activities will generate noise or other impacts, and must occur during nighttime hours when multiple travel lanes on I-66 can be closed. When those activities occur, measures will be taken to minimize impacts as much as feasible, including:

  • Demolished concrete will be hauled during daytime hours when possible and will be processed off site
  • Work area lighting will be directed towards roadway/away from residences
  • Dust control measures will be in place
  • Construction vibration and noise will be monitored
  • Portions of the bridge not over I-66 and the Metrorail tracks will be demolished during daytime hours when possible

Project emails and this website will be used to communicate major traffic switches and nighttime work.

What Drivers Can Expect

The Cedar Lane bridge over I-66 closed for about six months on May 15, 2020. A posted detour routes drivers to Gallows Road to cross I-66 using either Cottage Street (north side of I-66) or Hilltop Road and Lee Highway (south side of I-66). 

Drivers on I-66 will encounter lane shifts, lane closures, and overnight stoppages to accommodate bridge construction activities. Sign up for project email updates to keep up to date.

Changes for Pedestrians, Cyclists, and Bus Passengers

During the Cedar Lane bridge closure, pedestrians and cyclists have a marked detour using existing sidewalks and shared-use path to cross I-66 near the Dunn Loring-Merrifield Metrorail Station. The detour uses sidewalks along Cottage Street on the north side of I-66, shared-use path along Gallows Road, and multiple sidewalks on the south side of I-66.

Expanded Service and Route Changes for Fairfax Connector Buses

Fairfax Connector Routes 467/462 use the Cedar Lane bridge to travel between the Dunn Loring-Merrifield Metrorail station and stops in Vienna and Tysons. These routes have been modified during the bridge closure and will provide additional service on weekdays and weekends. Service on these routes is FREE for the duration of the bridge closure. For schedule information, visit www.fairfaxconnector.com or call 703-339-7200, TTY 711 (Se habla Español).

Cedar Lane Bridge Reconstruction Video Presentation

Bicycle and Pedestrian Improvements with the New Bridge

The new bridge will include a shared-use path on the east side and a sidewalk on the west side. Just north of I-66, there will be a connection to the 10-foot-wide shared-use path that is being built parallel to I-66 from Dunn Loring to Centreville as part of the project. This paved trail will provide cyclists and pedestrians with off-road access to Metrorail stations, parks, neighborhoods, and other trails. Learn more here.

Timeline

Anticipated Schedule Dates
Cedar Lane closes between Cottage Street and Hilltop Road
May 15, 2020
Bridge demolition
May to June 2020
Construction of new bridge abutments and piers
May to August 2020
Bridge re-opens
November 2020
Express lanes open December 2022

Resources

Fairfax Connector Bus Schedule - Website
Project Plan Sheet for Cedar Lane Area - PDF, 12MB
Cedar Lane Demolition and Construction Information Flyer (English) - PDF, 1.6MB
Cedar Lane Demolition and Construction Information Flyer (Spanish) - PDF, 1.3MB
Cedar Lane detour flyer (English) - PDF, 2.5MB
Cedar Lane detour flyer (Spanish) - PDF, 2.4MB
Cedar Lane Bridge Reconstruction Video Presentation Website
Presentación en video de construcción del puente Cedar Lane - Website