Construction Activities in October 

66 OTB Lane Shifts Aug-Sept 2018Drivers can expect to see lane shifts, lane restriping, and concrete barriers installed in the following areas:

Crews will also begin excavation for the new E.C. Lawrence Park Access Road, which will provide safer access to the park. This work is being coordinated with the Fairfax County Park Authority. Tree clearing will continue within the Chain Bridge Road (Route 123) and Route 28 interchanges, and along the project corridor within the VDOT right of way where barriers are set. Excavation will also begin in the Route 28 southeast loop.

Work will continue in the median of I-66 between Route 123 and Blake Lane to support upcoming traffic shifts. Asphalt will be placed and the lanes will be shifted left onto the new surface.