Overnight Full Closure of I-66 East and West at Route 123, May 7-8, for Bridge Beam Installation. Learn more.

News & Events

News Releases


Gallows Road over I-66 to Be Reduced to Two Lanes During Overnight Hours May 10-15

FAIRFAX – Gallows Road over I-66 will be reduced to a single travel lane in each direction Monday night, May 10, through Saturday night, May 15, from 8 p.m. to 6 a.m. each night. The southbound side of Gallows Road will be closed with two-way traffic running on the northbound side. The closures are necessary for utility work on the bridge as part of the Transform 66 Outside the Beltway Project.

READ FULL RELEASE



Overnight Full Closures of I-66 West at I-495 Next Week for Continued Overhead Bridge Work

FAIRFAX – Nightly lane closures, ramp closures, and traffic stoppages will be needed next week on I-66 West at I-495 Monday, May 10, through Saturday, May 15, as bridge beam installation continues at the I-66/I-495 Interchange as part of the Transform 66 Outside the Beltway Project. 

READ FULL RELEASE



Overnight Ramp Closures at Multiple Interchanges Next Week for the Transform 66 Outside the Beltway Project

FAIRFAX – Temporary ramp closures are scheduled to occur during the overnight hours next week at several I-66 interchanges as part of the Transform 66 Outside the Beltway Project.

READ FULL RELEASE



New Jermantown Road Bridge Over I-66 to Open on or about May 13; Demolition of Current Bridge Planned to Begin on or about May 14

FAIRFAX – The new Jermantown Road Bridge over I-66 is planned to open next week, with demolition of the old bridge to begin the following night. Jermantown Road traffic is scheduled to be shifted to the new crossing over I-66 on or about Thursday, May 13, with demolition to begin on Friday night, May 14. 

READ FULL RELEASE



Overnight Full Closure of I-66 East and West at Route 123 (Chain Bridge Road) Planned This Weekend, May 7-8, for Bridge Beam Installation

FAIRFAX – All lanes of I-66 East and West approaching Route 123 (Chain Bridge Road) are scheduled to be closed during the overnight hours May 7-8 to allow for installation of bridge beams for the new Route 123 South Bridge over I-66 as part of the Transform 66 Outside the Beltway Project. I-66 traffic will be detoured around the closure using the ramps at the Route 123 Interchange. Route 123 will remain open during these operations, but drivers should expect possible delays crossing over I-66. Police will be on scene to direct traffic.

READ FULL RELEASE